Land use planning in the vicinity of pipeline systems

Logo
CSA Group
Standards Development Organisation:
Working Program:
Designation Number:
CSA Z663
Standard Type:
National Standard of Canada - Domestic
Standard Development Activity:
Reaffirmation
ICS code(s):
75.200
Status:
Proceeding to development
SDO Comment Period Start Date:
SDO Comment Period End Date:
Posted On:

Scope:

Scope

1.1

This Standard

 

a) provides minimum requirements, guidance, and best practices for land use planning and development processes in the vicinity of existing pipeline systems;

 

b) addresses roles, responsibilities, and engagement of all stakeholders to establish a consistent approach to land use planning in the vicinity of existing pipeline systems; and

 

c) focuses on long-range policy planning and site development planning processes in the vicinity of existing pipeline systems.

 

Note: Annex B provides additional topics and guidance that is not covered in this Standard but deemed beneficial to have available.

 

1.2

This Standard does not apply to

 

a) infrastructure other than pipeline systems, including but not limited to

 

  i) potable water;

 

  ii) sewage;

 

  iii) stormwater; and

 

  iv) electric supply and communication.

 

b) sour gas pipeline systems addressed in CAN/CSA-Z662 and various provincial and/or federal legislation and regulation; and

 

c) planning and installation of future pipeline systems.

 

Note: See Figure 1.

 

1.3

In this Standard, shall is used to express a requirement, i.e., a provision that the user is obliged to satisfy in order to comply with the Standard; should is used to express a recommendation or that which is advised but not required; and may is used to express an option or that which is permissible within the limits of the Standard.

 

Notes accompanying clauses do not include requirements or alternative requirements; the purpose of a note accompanying a clause is to separate from the text explanatory or informative material.

 

Notes to tables and figures are considered part of the table or figure and may be written as requirements.

 

Annexes are designated normative (mandatory) or informative (non-mandatory) to define their application.

Project need:

Project Need
To review the Standard within the required 5 year period.

Note: The information provided above was obtained by the Standards Council of Canada (SCC) and is provided as part of a centralized, transparent notification system for new standards development. The system allows SCC-accredited Standards Development Organizations (SDOs), and members of the public, to be informed of new work in Canadian standards development, and allows SCC-accredited SDOs to identify and resolve potential duplication of standards and effort.

Individual SDOs are responsible for the content and accuracy of the information presented here. The text is presented in the language in which it was provided to SCC.